logo
ホーム >

最近の会社事件について Xi'an Xu&Hui Electromechanical Technology Co., Ltd. 認証

Tongchuan PV Plant Underground Cable Fault Precision Location — Rapid Detection Restores Solar Generation

2026-07-20

最近の会社事件について Tongchuan PV Plant Underground Cable Fault Precision Location — Rapid Detection Restores Solar Generation

Tongchuan PV Plant Underground Cable Fault Precision Location — Rapid Detection Restores Solar Generation

Integrated Cable Fault Detection System Deployed at Utility-Scale Solar Plant — Same-Day Fault Location with 0.1m Accuracy Despite High-Resistance Fault and Railway Noise Interference

0.1m
Pinpointing Accuracy
80–90m
Fault Distance
Same Day
Detection-to-Repair
5
Instruments Deployed
~900m
Cable Route Length

Project Background

Item Detail
Project Tongchuan Photovoltaic Power Plant — Low-Voltage Cable Fault Detection
Location Tongchuan, Shaanxi Province, China
Date June 7, 2026
Personnel Li Cheng, Gao Fei, Du Chaochao
Cable Type Single-core unarmoured low-voltage cable, bundled in groups of several dozen parallel cables
Cable Length Approximately 800–900 metres (PV panels to inverter)
Installation Primarily inside protective conduit, with sections of direct-buried at 0.3–1.0m depth
Site Conditions Adjacent to Longhai Railway — frequent passing trains generate substantial ambient noise

project detail photos

Fault Challenge

The on-site investigation presented multiple compounding difficulties that tested the limits of conventional cable fault detection methods:

Challenge Impact on Detection
High-Resistance Fault
~2 MΩ red phase to ground
Weak discharge acoustics during HV impulse testing — traditional acoustic pinpointing unreliable
Inconsistent Pre-Location
TDR reading >1,000m vs known ~900m
Wave velocity calibration error produced misleading distance; phase-to-phase measured ~5 kΩ indicating compound fault
Unreliable Waveforms
4–5 attempts per capture
High-resistance fault required repeated HV discharge cycles to produce usable waveform data
Railway Noise Interference
Continuous high-decibel train noise
Acoustic-only pinpointing rendered ineffective — operator unable to distinguish fault discharge from environmental noise
Dense Cable Bundle
Dozens of parallel cables
Positive identification of faulted cable among adjacent live circuits critical to avoid unnecessary excavation

Solution — Integrated Detection System

XZH TEST deployed a comprehensive five-instrument diagnostic chain covering the complete fault location workflow:

# Instrument Model Role in Detection Chain
1 ARC Multi-Pulse Pre-Locator XHGG502 High-precision fault distance measurement using 8-pulse ARC technology; converts complex high-resistance fault waveforms into interpretable short-circuit equivalent traces
2 Digital Fault Pinpointer XHDD503E Acoustic-magnetic synchronous pinpointing with 0.1m accuracy; immune to ambient noise through dual-signal time-difference analysis
3 Cable Pipe Locator XHGX507C Cable route verification and depth measurement along the full 800m+ path
4 Integrated Surge Generator XHHV515-8L Controlled high-voltage impulse delivery for reliable fault-point arc discharge
5 Cable Outer Sheath Tester XHHV523L Supplementary fault zone narrowing through sheath integrity analysis

Implementation Process

Step Operation Instrument Findings
1 Route Verification XHGX507C Re-surveyed full ~800–900m underground cable path from PV panels to inverter; confirmed route despite challenging high-resistance ground conditions
2 Fault Characterization Insulation Tester, Multimeter Red phase confirmed open-circuit; insulation: ~2 MΩ (PV end), ~2–3 MΩ (inverter end); phase-to-phase: ~5 kΩ — compound ground leakage + inter-phase fault
3 Fault Pre-Location XHGG502 Connected at inverter end; red phase HV + black phase grounded → fault distance: 80–90 metres; PV end phases shorted to ground to improve discharge reliability for pinpointing
4 Precision Pinpointing XHDD503E Walked cable path with acoustic-magnetic probe; discharge sound detected near fence line despite railway noise; magnetic time-difference confirmed fault location
5 Excavation & Verification Single-point excavation at pinpointed location; root cause: fence post installation hole directly penetrated cable, severing red phase conductor; confirmed within 0.1m accuracy

project detail photosproject detail photos

Application Results

Metric Result
Fault Location Accuracy Within 0.1m — excavation directly above fault point, no exploratory digging required
Pre-Location Distance 80–90 metres from inverter end (confirmed at excavation)
Detection Timeline Same-day completion — from initial testing through final pinpointing
Excavation Efficiency Single pinpointed location; zero trial trenches; zero collateral damage to adjacent cables
Root Cause Third-party damage: fence post installation hole penetrated cable conductor
Noise Immunity Acoustic-magnetic technology maintained reliable operation despite adjacent railway noise

project detail photos

Customer Value

  • Minimized Generation Downtime: Same-day fault location enabled immediate repair scheduling. The faulted PV string was restored to full generation capacity with minimal revenue loss — critical for a utility-scale solar asset where every hour of downtime translates to measurable financial impact.
  • Precision Excavation — Zero Waste: 0.1m pinpointing accuracy meant the repair crew excavated exactly at the fault location. No trial trenches, no unnecessary cable exposure, and no collateral damage to adjacent healthy cables in the tightly bundled group of several dozen parallel circuits.
  • Railway-Proven Noise Immunity: The site's proximity to the Longhai Railway would have rendered a conventional acoustic-only pinpointer unusable. The XHDD503E's acoustic-magnetic synchronous technology continuously delivered reliable time-difference data regardless of passing train noise — validating the technology for high-noise industrial environments.
  • Complete In-House Diagnostic Capability: The five-instrument suite provided a seamless diagnostic chain from initial fault characterization to centimetre-level excavation. No third-party equipment or external service providers were required — reducing both cost and logistical complexity.
  • Root Cause Documentation & Accountability: Positive identification of the fence installation as the fault cause provided the plant operator with concrete evidence for contractor accountability and informed future cable protection protocols during on-site construction activities.
Contact XZH TEST for technical consultation, on-site demonstration, or custom cable fault detection solutions tailored to your infrastructure.